MAJOR DEVELOPMENTAL PROJECTS / WORKS OF KARAIKAL DISTRICT
Sl.
No.
Name of the Department Major Projects / Works Present status as on 25.7.2006 Probable date of Completion
         
1  Education a) Central Kitchen in Thirunallar Commune Site to be handed over to PWD and Estimates to be prepared. Jul-07
         
        " b) Rural Playgrounds in all Communes Suitable land identified in all communes  
         
        " c) Construction of Youth Hostel in Karaikal. Site to be handed over to PWD and Estimates to be prepared. Dec-07
         
  " d) Construction of new building complex for Avvaiyar Govt. College for Women H.L.C. Clearance to be obtained. Estimates to be prepared.  
         
  " e) Construction of Standard Cricket Stadium. Administrative approval obtained. Land acquistion to be initiated.  
           
           
2  Electricity a) Sub-station in Polagam Growth Centre 110/11 KV Sub Station at Polagam included in 2007-08 Draft Annual Plan Mar-08
         
        " b) Sodium Vapour Conversion Programme in Bharathiyar Road, Church Street, Kamarajar Salai, Ambedkar Street, Eastern Bye-pass Road, Puliankottai Salai PWD to execute the border to border work. For Eastern Byepass Road & Puliankottai Salai  the Soundness Certificates  to be issued by the Commissioner, KM. Nov'06
         
    c Laying of underground Cable system in Karaikal Town and Coastal areas. Target during the current year - 5 kms. Remaining portion in the next year. March'07
           
3  Fisheries  Modern Fishing Harbour Rs.2 crore released. Tender to be settled for I phase work for Rs.20 lakhs. II Instalement is awaited from the Govt. Mar-08
           
4  Health a) Improvement of Existing General Hospital Work is in progress Dec'07
         
        " b) Acquisition of land for the construction of New General Hospital with Super Speciality Depts. Administrative approval obtained. Proposal under process for site selection and land acquistion.  
         
           
           
5  PIPDIC  Setting up of Industries in Polagam Growth Centre, T.R.Pattinam Steps to be taken for marketing of developed lands.  
         
           
         
6  PWD -
( B& R )
a)  Acquisition of land for Western Bye- pass for Karaikal. Administrative approval obtained. Land acquisition is in proress Dec'09
         
  " b) Preparation of Alignment for Eastern Bye-pass for T.R.Pattinam. MOST alignment obtained.Estimates under preparation Dec'09
         
        " c)  Construction of Indoor Stadium at Keezhaveli. Work commenced Dec'07
         
    d) Preparation of Estimates for Outdoor Stadium Estimates under preparation for Tennis court. Dec'08
         
        " e) Relaying of :    
    1) Marine Drive Beach Road Work is in progress Dec'06
    2) Arasalar Beach Road Work is in progress Dec'06
    3)  Mandapathur Road Work is in progress Dec'06
    4) Old Tranquebar Road Work is in progress Dec'06
    5)Pettai Road expansion Work completed  
         
  " f) Construction of Entrance arch at Nandalar & Nagore Borders For Nandalar Work order issued & for Nagore estimate under preparation Mar'07 &
Dec'07
         
  " g) Construction of new Collectorat Administrative approval awaitted. Land acquisition to be expedited. Dec'07
         
  " h) Reconstruction of bridges across Arasalar Thirumalairajanar and Vanjiar For Arasalar work re-tender called for.
For Thirumalairayanar Estimate submitted to Govt at a cost of Rs.8.00 crores
Dec'07


           


Mar'08
           
   PWD -
( B& R ) (Contd.)
I) Development of Police Parade Ground and construction of barracks Estmates  sent for sanction Dec'07
           
        " j) Land acquisition for laying parallel road to Thirunallar Alignment survey to be expedited Dec'08
         
    k) Reconstruction of Old Sea Wall Tenders to be finalised July'07
         
    l) Formation of Storm Water Drainage in NH 45-A from border to border Estimate to be prepared. Dec'07
         
    m) Construction of Marrine Police Station Architectural Plan to be prepared Dec'06
         
7  PWD - ( I & PH ) a)  Digging of Mini Lakes    
    1)  Nallambal Work is in progress Auguest'06
    2) Andodor - Ponbethi 4 (1) Notification issued.Estmate for Rs.87.00 Lakhs  submitted to S.E July'07
    3)  Thenoor 4(1) Notification to be issued July'07
    4)  Sethur -do- July'07
    5)  Ambagarathur -do- July'07
    6)  Padutharkollai -do- July'07
         
        " b)  Construction of Tail-end dam across:    
    1) Pravadaiyanar G.O received for Rs.1.97 crore.Tenders called for July'07
    2) Mullaiyar River Estimate re-submitted for Rs.70 lakhs July'07
    3) Vanjiar Estimate re-submitted for Rs.1.21crore July'07
         
    c) Undergroudn Sewerage Project Three detailed estimates submitted to C.E.Draft inseption and design proposals are to be approved by C.E July'09
         
        " d) Drainage Master Plan for Karaikal Town. For improvement of three major drainage channels. Detailed survey under progress estimates for Rs.48.00 Crore submitted to C.E Dec'07
         
    e) Construction of raised protection walls (60 cms. Above maximum flood level) in Arasalar and Vanjiyar with inspection track Estimates for 12.00 Crore submitted to Govt. for sanction  
    f) Widening and formation of mini lakes along Arasalar I)At Pettai -Work completed
 II) Revised estimates for Rs.66.58 Lakhs re-submitted to Govt.
Mar'07
           
8  Karaikal Municipality a) Improvement of the site near Murugaram Nagar for Whole sale Market Earth filling completed Dec'07
           
        " b)  Land acquisition for New Modern Bus  Stand Administrative approval awaited from LAD Aug.07
           
        " c)  Conversion of Rex Theatre into  Kalaiarangam Work nearing compeltion. Inauguaration will be held shortly. Sept.06
           
    d) Creation of Gardens and Tourist Vehicle Parking bays at the Old Bus Stand Site A comprehensive remunerative plan for Multi Complex  to be prepared  
           
9  Tourism a) Construction of Tourist Hotel at Beach Road After vacating PRTC work shop work will be started. Mar-08
           
        " b) Setting up of Airport at Karaikal Site selection is in progress Dec.06
           
    c) Execution of 'INTAC's Beach Beautification Plan Fullfledged plan to be submitted July'07
           
    d) Execution of 'HUDCO's Thirunallar Temple Town Development Plan Project report submitted to Govt.  Establishment of an Automonous Society is in progress.  Land Acquisition to be expedited.  
           
    e) Construction of Yatri Nivas at Thirunallar Work is In progress. Additional fund is required.  
           
10 Port   Establishment of Shipping  Port at Vanjore Land handed over to Port  
           
           
           
11 Planning and Research a) a) Construction of bridges for Nagore - Karaikal Broad gauge Railway Project Vettar bridge work 50% completed .For other bridges tenders are to be called for.  
    b) Conduct of Survey for Karaikal - Thirunallar - Tranquebar - Mayiladuthurai Broad Gauge Railway Project Survey under progress.  
           
    c) Widening of Sirkazhi - Karaikal N.H. 45A Widening work is in progress up to Thirukkadaiyur  
           
    d) Upgradation of Karaikal - Kumbakonam - Thanjavur Road, Karaikal - Thiruvarur and Karaikal - Mayiladuthurai into National Highway Request made to Ministry of Surface Transport, New Delhi.